October 15, 2009

After a dozen years, SR 519 comes together

  • When finished next June, the project's $84.4 million second phase will separate trains and transit from cars and pedestrians near Safeco Field.
  • By MARC STILES
    Journal Staff Reporter

    Images courtesy of WSDOT [enlarge]
    The ramp in the foreground is for westbound motor vehicles coming off of the interstates. A new overpass along South Royal Brougham Way crosses over railroad tracks.

    THE $84.4 MILLION second phase of the state Route 519 project in Seattle's Sodo area is a bit like a physics puzzle with time, mass and weight as the parts of the equation.

    . . .

    To read this story in full login or purchase a subscription.


    Previous columns:

    Search Stories
     Find:
     With:
     In:
     Depth:
     Sort by:
    Advanced options
     
     
     
     
     
     
     
     
     
     
     
     


    Copyright ©2009 Daily Journal of Commerce, Inc. and djc.com.
    Comments? Questions? Contact us.
    Building Permits

     

    Email to a friend
    Print
    Comment
    Reprints
    Add to myDJC